Atlantic Corridor / Galicia
Milestones

Milestone-by-milestone audit

We compare, milestone by milestone, the promised date with the actual one. The delay is measured only against the first committed delivery date —never against the tender date— and actions with no public date are excluded from the count. Every re-announcement is logged with its source.

Data as of: 1 Jun 2026

01Cumulative delay

21 years

Sum of slippages of 10 milestones with a target date

02Average delay

2y 1m

Average slippage per milestone

03On-time milestones

50%

5 of 10 with a target date

04Worst delay

11y 12m

Commercial opening of Madrid - Galicia HSR (Olmedo - Ourense)

Composition of cumulative delay

6 re-announcements logged

The total is the sum of individual slippages of parallel actions; it does not represent a sequential time period.

  • 19y 3m · 92%

    Consolidated (delivered)

    Historical delay of milestones already in service.

  • 1y 5m · 7%

    Committed (pending)

    Slippage of the delivery date of milestones not yet completed.

  • 4 months · 2%

    Overdue, not completed

    Days elapsed beyond the latest promise without delivery.

Showing 48 of 48 milestones.