Milestone-by-milestone audit
We compare, milestone by milestone, the promised date with the actual one. The delay is measured only against the first committed delivery date —never against the tender date— and actions with no public date are excluded from the count. Every re-announcement is logged with its source.
01Cumulative delay
21 years
Sum of slippages of 10 milestones with a target date
02Average delay
2y 1m
Average slippage per milestone
03On-time milestones
50%
5 of 10 with a target date
04Worst delay
11y 12m
Commercial opening of Madrid - Galicia HSR (Olmedo - Ourense)
Composition of cumulative delay
6 re-announcements loggedThe total is the sum of individual slippages of parallel actions; it does not represent a sequential time period.
19y 3m · 92%
Consolidated (delivered)
Historical delay of milestones already in service.
1y 5m · 7%
Committed (pending)
Slippage of the delivery date of milestones not yet completed.
4 months · 2%
Overdue, not completed
Days elapsed beyond the latest promise without delivery.
| Segment | Status | Re-announcements | ||||
|---|---|---|---|---|---|---|
| Commercial opening of Madrid - Galicia HSR (Olmedo - Ourense) | Madrid - Galicia HSR (Olmedo - Ourense) | Completed | 11y 12m of delay | 21 Dec 2021 | — | 3 |
| Completion of the A Coruña - Vigo Atlantic Axis | Atlantic Axis A Coruña - Vigo | Completed | 7y 4m of delay | 18 Apr 2015 | — | 1 |
| Rail access to Ferrol Outer Port (Cabo Prioriño) | Ferrol port rail access | Under construction | 1 years of delay | 31 Dec 2026 | €120 M | 1 |
| PLISAN rail siding (Salvaterra de Miño - As Neves) | Port of Vigo rail accesses (Bouzas, Guixar, PLISAN) | Under construction | 5 months of delay | 31 May 2026 | €40 M | 1 |
| Elimination of two level crossings (Rioseco and Juan Montes) in the urban core of Monforte de Lemos (León–A Coruña line) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Stopped | 4 months of delay | 31 Jan 2026 | — | — |
| 750 m sidings León - Monforte | León - Monforte de Lemos access | Planned | No target date | — | — | — |
| Ourense intermodal station (HSR integration) | Madrid - Galicia HSR (Olmedo - Ourense) | Under construction | No target date | — | €112 M | — |
| Miño Line upgrade (Vigo-Guixar - Redondela) for freight | Vigo - Ourense connection (Miño Line / Cerdedo bypass) | Under construction | No target date | — | €69 M | — |
| Vigo Southern rail exit (toward the Portuguese border) | Vigo Southern Exit | Planned | No target date | — | €687 M | — |
| Direct Vigo - Ourense HSR via Cerdedo | Vigo - Ourense connection (Miño Line / Cerdedo bypass) | Planned | No target date | — | — | — |
| Rail access to A Coruña Outer Port (Punta Langosteira) | A Coruña Outer Port rail access | Under construction | On time | 31 Dec 2027 | €160 M | — |
| Renewal and upgrade of the rail branch to Ferrol Inner Port | Ferrol port rail access | Under construction | No target date | — | €28 M | — |
| Removal of level crossings on the Port of Marín branch (Os Praceres) | Marín - Pontevedra port access branch | Stopped | No target date | — | €9 M | — |
| Rail connection of the Bouzas terminal (Port of Vigo) | Port of Vigo rail accesses (Bouzas, Guixar, PLISAN) | Planned | No target date | — | — | — |
| Ourense - Monforte de Lemos - Lugo upgrade and electrification (line 810/800) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | €626 M | — |
| ERTMS deployment on the Atlantic Axis (A Coruña–Vigo) and Ourense–Santiago extension | Atlantic Axis A Coruña - Vigo | Completed | No target date | — | — | — |
| Feasibility and preliminary studies for the Atlantic Axis extension: O Porriño–Portuguese border | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
| Track renewal on the Miño Line: Vigo Guixar–Redondela (13 km) | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
| Safety systems adaptation and 25 kV electrification preparation: Vigo Guixar–Redondela (Miño Line / L812) | Atlantic Axis A Coruña - Vigo | Under tender | No target date | — | €14 M | — |
| Comprehensive modernisation of the Guillarei–Redondela section (Miño Line) | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
| Comprehensive renewal of the Redondela–Arcade Junction section (Redondela–Santiago line) | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
| Engineering design for track renewal: Ourense–Guillarei section (Miño Line, line 810) | Atlantic Axis A Coruña - Vigo | Planned | No target date | — | — | — |
| Construction supervision and quality control: Guillarei–Redondela track renewal (Miño Line) | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
| New electronic interlockings at Vigo-Guixar, Redondela and Chapela Junction (Miño Line) | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
| 750 m passing loop at As Gándaras siding (O Porriño) | Atlantic Axis A Coruña - Vigo | Completed | No target date | — | — | — |
| Electrification and comprehensive renewal: Guillarei–Tui–Portuguese border (Guillarei–Valença do Minho line) | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | €12 M | — |
| Southern access branch to Langosteira and new Uxes freight terminal (A Coruña) | A Coruña Outer Port rail access | Planned | No target date | — | — | — |
| Comprehensive remodelling of A Coruña–San Cristóbal station | Madrid - Galicia HSR (Olmedo - Ourense) | Under construction | On time | 15 Jul 2026 | €87 M | — |
| Accessibility upgrade and remodelling of Redondela station | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
| New Valga halt on the A Coruña–Vigo line — alternatives study and construction project design | Atlantic Axis A Coruña - Vigo | Under tender | No target date | — | €213,785 | — |
| Elimination of two level crossings in Valga (Vilagarcía de Arousa–Angueira Junction line) | Atlantic Axis A Coruña - Vigo | Completed | No target date | 29 Oct 2025 | €3 M | — |
| GSM-R telecommunications modernisation on the Medina del Campo–Ourense line | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | — | — |
| New power and fibre-optic system on the Medina del Campo–Ourense line | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | — | — |
| Waterproofing of the Das Maceiras tunnel (La Madroa), LAV access to Vigo-Urzaiz | Madrid - Galicia HSR (Olmedo - Ourense) | Planned | No target date | — | — | — |
| Overhead line renewal to 25 kV AC on the Ourense–Monforte de Lemos section | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | — | — |
| New 25 kV AC electrification on the Monforte de Lemos–Lugo section | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | — | — |
| New Oural tunnel (Ourense–Monforte de Lemos–Lugo corridor) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Completed | On time | 23 Sep 2025 | — | — |
| New Lugo intermodal station (rail + bus) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | On time | 30 Jun 2026 | — | — |
| Elimination of six level crossings in the municipality of Lugo (León–A Coruña line) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | — | — |
| Elimination of four level crossings in Sarria (PK 389/262–392/136, León–A Coruña line 800) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | — | — |
| Elimination of seven level crossings in Ourense and Sarria (Ourense–Monforte de Lemos–Lugo line) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | — | — |
| Elimination of 10 level crossings in the municipalities of Lugo and Sarria (Monforte de Lemos–Lugo–A Coruña line) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Under construction | No target date | — | €6 M | — |
| Slope stabilisation on line 740 Ferrol–Pravia, Ferrol–Viveiro section (km 19+000–40+000) | Ferrol port rail access | Under construction | No target date | — | — | — |
| APFSC complementary rail works at Ferrol inner port (yard track, holding track and access branch with third rail) | Ferrol port rail access | Under construction | On time | 30 Jun 2026 | — | — |
| Preliminary alignment study for the standard-gauge bypass connecting León–A Coruña and Betanzos Infesta–Ferrol lines (Betanzos bypass) | Ferrol port rail access | Planned | No target date | — | — | — |
| Feasibility study for a new Lugo–Santiago de Compostela rail link (new variant on the León–A Coruña line / Atlantic Axis) | Ourense - Monforte de Lemos - Lugo axis (line 810/800) | Planned | No target date | — | — | — |
| Noise barriers on the Atlantic Axis, Vigo–Padrón section | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
| Noise barriers on the Atlantic Axis, Padrón–A Coruña section | Atlantic Axis A Coruña - Vigo | Under construction | No target date | — | — | — |
Showing 48 of 48 milestones.