Milestone-by-milestone audit
We compare, milestone by milestone, the promised date with the actual one. The delay is measured only against the first committed delivery date —never against the tender date— and actions with no public date are excluded from the count. Every re-announcement is logged with its source.
01Cumulative delay
20y 9m
Sum of slippages of 5 milestones with a target date
02Average delay
4y 2m
Average slippage per milestone
03On-time milestones
20%
1 of 5 with a target date
04Worst delay
11y 12m
Commercial opening of Madrid - Galicia HSR (Olmedo - Ourense)
Composition of cumulative delay
6 re-announcements loggedThe total is the sum of individual slippages of parallel actions; it does not represent a sequential time period.
19y 3m · 93%
Consolidated (delivered)
Historical delay of milestones already in service.
1y 5m · 7%
Committed (pending)
Slippage of the delivery date of milestones not yet completed.
1 d · 0%
Overdue, not completed
Days elapsed beyond the latest promise without delivery.
Showing 14 of 14 milestones.