Atlantic Corridor / Asturias
Milestones

Milestone-by-milestone audit

We compare, milestone by milestone, the promised date with the actual one. The delay is measured only against the first committed delivery date —never against the tender date— and actions with no public date are excluded from the count. Every re-announcement is logged with its source.

Data as of: 1 Jun 2026

01Cumulative delay

69y 9m

Sum of slippages of 10 milestones with a target date

02Average delay

6y 12m

Average slippage per milestone

03On-time milestones

30%

3 of 10 with a target date

04Worst delay

19y 6m

Plan de Vías de Gijón — soterramiento e integración

Composition of cumulative delay

15 re-announcements logged

The total is the sum of individual slippages of parallel actions; it does not represent a sequential time period.

  • 29y 3m · 42%

    Consolidated (delivered)

    Historical delay of milestones already in service.

  • 40y 5m · 58%

    Committed (pending)

    Slippage of the delivery date of milestones not yet completed.

Showing 35 of 35 milestones.