Atlantic Corridor / León
Milestones

Milestone-by-milestone audit

We compare, milestone by milestone, the promised date with the actual one. The delay is measured only against the first committed delivery date —never against the tender date— and actions with no public date are excluded from the count. Every re-announcement is logged with its source.

Data as of: 1 Jun 2026

01Cumulative delay

27y 2m

Sum of slippages of 5 milestones with a target date

02Average delay

5y 5m

Average slippage per milestone

03On-time milestones

40%

2 of 5 with a target date

04Worst delay

14y 11m

Commercial opening of the Pajares Bypass (passengers)

Composition of cumulative delay

6 re-announcements logged

The total is the sum of individual slippages of parallel actions; it does not represent a sequential time period.

  • 19y 8m · 72%

    Consolidated (delivered)

    Historical delay of milestones already in service.

  • 7y 6m · 28%

    Committed (pending)

    Slippage of the delivery date of milestones not yet completed.

Showing 18 of 18 milestones.